Oil and Natural Gas Corporation Limited (ONGC) is preparing for the next phase of well control of well RDS#147A in Assam as part of its continued efforts to manage the gas discharge safely.
The expert team from the International Well Control Agency has reached the site today and is carrying out the preliminary assessment of the situation.
High-pressure water pumping is being carried out continuously in the range of 3000-3500 PSI with a high discharge rate of around 19-20 barrels per minute. Today, the total volume pumped is ~2200 barrels (BBLS), with one intermittent junk shot, forming a key component of the ongoing well control strategy.
Simultaneously, site levelling is in full swing, enabling smooth access and site readiness for the next phase of operations.

An alternate road ramp has been constructed to ensure safe and uninterrupted access to the well site for equipment and personnel.
Shielding of other wells within the cluster has also been completed as a precautionary measure to ensure safety during the upcoming stages of well control.
The gas composition has been tested and found to be within safe limits, offering additional assurance regarding the controlled nature of the current discharge. Meanwhile, the water level in the nearby Dikhow River is being closely monitored, with pumps strategically placed near the riverbank to support continuous water operations.
ONGC remains fully committed to ensuring public safety, environmental protection, and operational integrity through robust safety practices and expert collaboration.
Note
RDS: Rudrasagar
BBL: Barrel
PSI: Pounds per Square Inch
Frac Spread: A set of specialized equipment and machinery utilised in hydraulic fracturing (fracking) to implement advanced techniques such as "pressure pumping" for addressing issues like gas leaks.
Issued by:
Corporate Communications